AUS01 - Antara Living - Olympic Park
Bollettini recenti
  • 16th settembre 2024, Daily Prestart

    All workers have to Sign in daily
    - Peno covers must not be removed, Decode staff must be informed and appropriate exclusion zones or edge protection put in place before removal
    -Exclusion zone levels, 7 & 8,9,10 only form workers and scaffolders
    -Mobile plant in use basement levels B1, B2, B3
    -Exclusion zones in place
    -Mobile plant in operation marked blue
    - All site access to be clean and clear
    - PPE to be worn at all times on-site
    - All power tools and leads to be tagged
    - No Tolerance for any violent behavior
    - Any incident that occurs must be reported to the site office
    - Be aware of mobile plant and crane movement
    - Please be aware of traffic when crossing the road from the office into the job site
    - Use lead stands at all times
    - Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
    - All subcontractors must clean their working areas daily
    - All the trades on deck have to coordinate with each other during the work and work around each other without interrupting the job
    - All sediment control bags are to be checked daily
    - permits must be submitted and approved before any hot works activities stripping activities and any other activities that require permits if you are unsure speak to a decode representative
    - nurse calls are in place on all stair landings
    - The emergency assembly point is near the access gate on Murray Rose Ave next to the hoist
    - no smoking on site
    - new SDS must be uploaded as required
    - new equipment must be inducted into the site

    Daily Pre-Start Content:

    Hazards:
    Form workers starting level 12 deck
    Peno covers can not be removed
    Mobile plant in use basement levels
    No access to levels -8-9-10-11under formwork form worker only
    Exclusion zones in place marked red
    Mobile plant in operation marked blue
    PT working on level 12
    Plumbers level 4roughing in
    Gyprockers level 6 framing
    steel fixers top reo
    Pouring vertical level 11 to 12
    footpath closed

  • 25th luglio 2024,

    Daily Pre-Start Content:

    PRIVATE CERTIFIER INSPECTION

    -The exclusion zone on level 1 under the cup looks system
    -Exclusion zone levels, 6, 7 & 8 only form workers and scaffolders
    -Mobile plant in use basement levels B1, B2, B3
    -Exclusion zones in place
    -Mobile plant in operation marked blue
    - All site access to be clean and clear
    - PPE to be worn at all times on-site
    - All power tools and leads to be tagged
    - No Tolerance for any violent behavior
    - Any incident that occurs must be reported to the site office
    - Be aware of mobile plant and crane movement
    - Please be aware of traffic when crossing the road from the office into the job site
    - Use lead stands at all times
    - Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
    - All subcontractors must clean their working areas daily
    - All the trades on deck have to coordinate with each other during the work and work around each other without interrupting the job
    - All sediment control bags are to be checked daily
    - permits must be submitted and approved before any hot works activities stripping activities and any other activities that require permits if you are unsure speak to a decode representative
    - nurse calls are in place on all stair landings
    - The emergency assembly point is near the access gate on Murray Rose Ave next to the hoist
    - no smoking on site
    - new SDS must be uploaded as required
    - new equipment must be inducted into the site

    Daily Pre-Start Content:

    Site Activities:

    PRIVATE CERTIFIER INSPECTION
    - Skyscraper fixing door frame on level 4 , 5
    - Skyscraper to finish level 3, Hebel
    - Skyscraper corking and installing bottom and top angle level 3
    - Level 8 speed panel
    - Block layers level 1
    - Electrician level 3 roughing in
    - Plumbers level 2 rough in and corking
    - Mechanical level 2 & 3 roughing in
    - water proofer level 2 - 3 - 4 - 5 joint seal and primer slab edge and hobs
    - Steel fixes installing top steel on Level 09
    - Formwork back propping level 05 up.
    -Formworker start working on hobs and upturn.
    - Painters working on the lift 3 patching level 5 soffit
    -

    Allegati :
    Antara -Daily Pre-Start Notice Board - 24-07-24 Autosaved Autosaved.pdf
  • 14th giugno 2024, Daily Pre-start

    - cup lock system from levels 3 to 7
    - Lovel 00 and level 1 Door installation
    - level 00 - 1 waterproof preparation
    - level 6 internal stud walls set out
    - DA fire atrium install level 4
    -FB masonry basement 1



    SERVICES:
    - Geminair level 00 level 5
    - Azure plumbing level 4 - 5
    - Ampcore level 1
    _Da Fire level 4


    Hazards
    Exclusion zone level ,6,7 form workers and scaffolders only
    Mobile plant in use basement levels
    Exclusion zones in place
    Mobile plant in operation marked blue
    - Sign In, daily
    - All site access to be clean and clear
    - PPE to be worn at all times on-site
    - All power tools and leads to be tagged
    - No Tolerance for any violent behaviour
    - Be aware of mobile plant and crane movement
    - Please be aware of traffic when crossing the road from the office into the job site
    - Use lead stands all times
    - Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
    - All subcontractors must clean their working areas daily
    - All the trades on deck have to coordinate between each other during the work and work around each other without interrupting of job progress

Previsioni meteo del cantiere
Meteo attuale del cantiere

Ultimo aggiornamento su: 22:21
Temperatura: 20C (App 20C)
Velocità del vento: 13KMH
Max. Vento: 28KMH @16:21
Pioggia dalle 9.00: 12,2mm
Temp min: 20C @22:20
Temp max: 32C @12:37 31/01/2026
Raffica: 17KMH
Raffiche max: 39KMH @16:21


Osservazione proveniente da - Bureau of Meteorology
Luogo di osservazione - Sydney Olympic Park, NEW SOUTH WALES
Fuso orario - Ora standard dell’Australia orientale
Previsioni - domenica, 1 febbraio

Cloudy.
Min: 17C Max: 23C
Possibilità di pioggia: 20%


Previsioni provenienti da - Bureau of Meteorology
Luogo previsioni - Sydney Olympic Park, NEW SOUTH WALES
Fuso orario - Ora standard dell’Australia orientale
Domani - lunedì, 2 febbraio

Cloudy.
Min: 18C Max: 25C
Possibilità di pioggia: 20%


Documenti importanti per il cantiere
Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

Nuovo sul cantiere?

Conosci i requisiti dei DPI per questo cantiere?

Assicurati di avere l'equipaggiamento di sicurezza corretto per il primo giorno in cantiere.

Visualizza requisiti DPI del cantiere

Nuovo sul cantiere?

Inizia a lavorare prima quando arrivi sul cantiere.

Completa la registrazione del cantiere online con la massima comodità e risparmia tempo.

Inizio registrazione

;