Últimos Boletines
  • 16th septiembre 2024, Daily Prestart

    All workers have to Sign in daily
    - Peno covers must not be removed, Decode staff must be informed and appropriate exclusion zones or edge protection put in place before removal
    -Exclusion zone levels, 7 & 8,9,10 only form workers and scaffolders
    -Mobile plant in use basement levels B1, B2, B3
    -Exclusion zones in place
    -Mobile plant in operation marked blue
    - All site access to be clean and clear
    - PPE to be worn at all times on-site
    - All power tools and leads to be tagged
    - No Tolerance for any violent behavior
    - Any incident that occurs must be reported to the site office
    - Be aware of mobile plant and crane movement
    - Please be aware of traffic when crossing the road from the office into the job site
    - Use lead stands at all times
    - Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
    - All subcontractors must clean their working areas daily
    - All the trades on deck have to coordinate with each other during the work and work around each other without interrupting the job
    - All sediment control bags are to be checked daily
    - permits must be submitted and approved before any hot works activities stripping activities and any other activities that require permits if you are unsure speak to a decode representative
    - nurse calls are in place on all stair landings
    - The emergency assembly point is near the access gate on Murray Rose Ave next to the hoist
    - no smoking on site
    - new SDS must be uploaded as required
    - new equipment must be inducted into the site

    Daily Pre-Start Content:

    Hazards:
    Form workers starting level 12 deck
    Peno covers can not be removed
    Mobile plant in use basement levels
    No access to levels -8-9-10-11under formwork form worker only
    Exclusion zones in place marked red
    Mobile plant in operation marked blue
    PT working on level 12
    Plumbers level 4roughing in
    Gyprockers level 6 framing
    steel fixers top reo
    Pouring vertical level 11 to 12
    footpath closed

  • 25th julio 2024,

    Daily Pre-Start Content:

    PRIVATE CERTIFIER INSPECTION

    -The exclusion zone on level 1 under the cup looks system
    -Exclusion zone levels, 6, 7 & 8 only form workers and scaffolders
    -Mobile plant in use basement levels B1, B2, B3
    -Exclusion zones in place
    -Mobile plant in operation marked blue
    - All site access to be clean and clear
    - PPE to be worn at all times on-site
    - All power tools and leads to be tagged
    - No Tolerance for any violent behavior
    - Any incident that occurs must be reported to the site office
    - Be aware of mobile plant and crane movement
    - Please be aware of traffic when crossing the road from the office into the job site
    - Use lead stands at all times
    - Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
    - All subcontractors must clean their working areas daily
    - All the trades on deck have to coordinate with each other during the work and work around each other without interrupting the job
    - All sediment control bags are to be checked daily
    - permits must be submitted and approved before any hot works activities stripping activities and any other activities that require permits if you are unsure speak to a decode representative
    - nurse calls are in place on all stair landings
    - The emergency assembly point is near the access gate on Murray Rose Ave next to the hoist
    - no smoking on site
    - new SDS must be uploaded as required
    - new equipment must be inducted into the site

    Daily Pre-Start Content:

    Site Activities:

    PRIVATE CERTIFIER INSPECTION
    - Skyscraper fixing door frame on level 4 , 5
    - Skyscraper to finish level 3, Hebel
    - Skyscraper corking and installing bottom and top angle level 3
    - Level 8 speed panel
    - Block layers level 1
    - Electrician level 3 roughing in
    - Plumbers level 2 rough in and corking
    - Mechanical level 2 & 3 roughing in
    - water proofer level 2 - 3 - 4 - 5 joint seal and primer slab edge and hobs
    - Steel fixes installing top steel on Level 09
    - Formwork back propping level 05 up.
    -Formworker start working on hobs and upturn.
    - Painters working on the lift 3 patching level 5 soffit
    -

    Archivos adjuntos :
    Antara -Daily Pre-Start Notice Board - 24-07-24 Autosaved Autosaved.pdf
  • 14th junio 2024, Daily Pre-start

    - cup lock system from levels 3 to 7
    - Lovel 00 and level 1 Door installation
    - level 00 - 1 waterproof preparation
    - level 6 internal stud walls set out
    - DA fire atrium install level 4
    -FB masonry basement 1



    SERVICES:
    - Geminair level 00 level 5
    - Azure plumbing level 4 - 5
    - Ampcore level 1
    _Da Fire level 4


    Hazards
    Exclusion zone level ,6,7 form workers and scaffolders only
    Mobile plant in use basement levels
    Exclusion zones in place
    Mobile plant in operation marked blue
    - Sign In, daily
    - All site access to be clean and clear
    - PPE to be worn at all times on-site
    - All power tools and leads to be tagged
    - No Tolerance for any violent behaviour
    - Be aware of mobile plant and crane movement
    - Please be aware of traffic when crossing the road from the office into the job site
    - Use lead stands all times
    - Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
    - All subcontractors must clean their working areas daily
    - All the trades on deck have to coordinate between each other during the work and work around each other without interrupting of job progress

Pronóstico del tiempo para la Obra
Tiempo en Obra actual

Última actualización el: 10:21 PM
Temperatura: 20C (Aplicación 20C)
Velocidad del viento: 13MPH
Máx. Viento: 28MPH @4:21 PM
Lluvia desde las 9 a.m.: 12.2mm
Temp mín: 20C @10:20 PM
Temp máx: 32C @12:37 PM 1/31/2026
Ráfaga: 17MPH
Ráfagas máx: 39MPH @4:21 PM


Observación obtenida de - Bureau of Meteorology
Lugar de observación - Sydney Olympic Park, NEW SOUTH WALES
Zona horaria - hora estándar de Australia oriental
Pronóstico - domingo, 1 febrero

Cloudy.
Mín: 17C Máx: 23C
Probabilidad de lluvia: 20%


Pronóstico obtenido de - Bureau of Meteorology
Lugar de la previsión - Sydney Olympic Park, NEW SOUTH WALES
Zona horaria - hora estándar de Australia oriental
Mañana - lunes, 2 febrero

Cloudy.
Mín: 18C Máx: 25C
Probabilidad de lluvia: 20%


Documentos importantes de la Obra
¿Primera vez en la Obra?

¿Conoce los requisitos de PPE para esta Obra?

Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.

Ver los requisitos de PPE para la Obra

Empiece a trabajar en cuanto llegue a la obra.

Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.

Comenzar registro

¿Primera vez en la Obra?

¿Conoce los requisitos de PPE para esta Obra?

Asegúrese de que cuento con el equipo de seguridad correcto para su primer día en la obra.

Ver los requisitos de PPE para la Obra

¿Primera vez en la Obra?

Empiece a trabajar en cuanto llegue a la obra.

Complete su registro de la obra en línea a su conveniencia y ahorre tiempo.

Comenzar registro

;