AUS01 - Antara Living - Olympic Park - 公共プロジェクト現場
-
16th 9月 2024, Daily Prestart
All workers have to Sign in daily
- Peno covers must not be removed, Decode staff must be informed and appropriate exclusion zones or edge protection put in place before removal
-Exclusion zone levels, 7 & 8,9,10 only form workers and scaffolders
-Mobile plant in use basement levels B1, B2, B3
-Exclusion zones in place
-Mobile plant in operation marked blue
- All site access to be clean and clear
- PPE to be worn at all times on-site
- All power tools and leads to be tagged
- No Tolerance for any violent behavior
- Any incident that occurs must be reported to the site office
- Be aware of mobile plant and crane movement
- Please be aware of traffic when crossing the road from the office into the job site
- Use lead stands at all times
- Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
- All subcontractors must clean their working areas daily
- All the trades on deck have to coordinate with each other during the work and work around each other without interrupting the job
- All sediment control bags are to be checked daily
- permits must be submitted and approved before any hot works activities stripping activities and any other activities that require permits if you are unsure speak to a decode representative
- nurse calls are in place on all stair landings
- The emergency assembly point is near the access gate on Murray Rose Ave next to the hoist
- no smoking on site
- new SDS must be uploaded as required
- new equipment must be inducted into the site
Daily Pre-Start Content:
Hazards:
Form workers starting level 12 deck
Peno covers can not be removed
Mobile plant in use basement levels
No access to levels -8-9-10-11under formwork form worker only
Exclusion zones in place marked red
Mobile plant in operation marked blue
PT working on level 12
Plumbers level 4roughing in
Gyprockers level 6 framing
steel fixers top reo
Pouring vertical level 11 to 12
footpath closed -
25th 7月 2024,
Daily Pre-Start Content:
添付ファイル :
PRIVATE CERTIFIER INSPECTION
-The exclusion zone on level 1 under the cup looks system
-Exclusion zone levels, 6, 7 & 8 only form workers and scaffolders
-Mobile plant in use basement levels B1, B2, B3
-Exclusion zones in place
-Mobile plant in operation marked blue
- All site access to be clean and clear
- PPE to be worn at all times on-site
- All power tools and leads to be tagged
- No Tolerance for any violent behavior
- Any incident that occurs must be reported to the site office
- Be aware of mobile plant and crane movement
- Please be aware of traffic when crossing the road from the office into the job site
- Use lead stands at all times
- Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
- All subcontractors must clean their working areas daily
- All the trades on deck have to coordinate with each other during the work and work around each other without interrupting the job
- All sediment control bags are to be checked daily
- permits must be submitted and approved before any hot works activities stripping activities and any other activities that require permits if you are unsure speak to a decode representative
- nurse calls are in place on all stair landings
- The emergency assembly point is near the access gate on Murray Rose Ave next to the hoist
- no smoking on site
- new SDS must be uploaded as required
- new equipment must be inducted into the site
Daily Pre-Start Content:
Site Activities:
PRIVATE CERTIFIER INSPECTION
- Skyscraper fixing door frame on level 4 , 5
- Skyscraper to finish level 3, Hebel
- Skyscraper corking and installing bottom and top angle level 3
- Level 8 speed panel
- Block layers level 1
- Electrician level 3 roughing in
- Plumbers level 2 rough in and corking
- Mechanical level 2 & 3 roughing in
- water proofer level 2 - 3 - 4 - 5 joint seal and primer slab edge and hobs
- Steel fixes installing top steel on Level 09
- Formwork back propping level 05 up.
-Formworker start working on hobs and upturn.
- Painters working on the lift 3 patching level 5 soffit
-
Antara -Daily Pre-Start Notice Board - 24-07-24 Autosaved Autosaved.pdf
-
14th 6月 2024, Daily Pre-start
- cup lock system from levels 3 to 7
- Lovel 00 and level 1 Door installation
- level 00 - 1 waterproof preparation
- level 6 internal stud walls set out
- DA fire atrium install level 4
-FB masonry basement 1
SERVICES:
- Geminair level 00 level 5
- Azure plumbing level 4 - 5
- Ampcore level 1
_Da Fire level 4
Hazards
Exclusion zone level ,6,7 form workers and scaffolders only
Mobile plant in use basement levels
Exclusion zones in place
Mobile plant in operation marked blue
- Sign In, daily
- All site access to be clean and clear
- PPE to be worn at all times on-site
- All power tools and leads to be tagged
- No Tolerance for any violent behaviour
- Be aware of mobile plant and crane movement
- Please be aware of traffic when crossing the road from the office into the job site
- Use lead stands all times
- Falling from Heights!!!! make sure all handrails are installed on every edge, only authorized personnel can remove handrails
- All subcontractors must clean their working areas daily
- All the trades on deck have to coordinate between each other during the work and work around each other without interrupting of job progress
現在の現場の天気
最終更新日時: 23:21
温度: 20C (アプリ 20C)
風速: 13KMH
最大風速: 28KMH @16:21
午前9時からの雨: 12.2mm
最低気温: 20C @23:20
最高気温: 32C @12:37 2026/01/31
突風: 15KMH
最大突風: 39KMH @16:21
観察場所 - Sydney Olympic Park, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
予測 - 日曜日, 1 2月
Cloudy.
分: 17C マックス: 23C
降雨の可能性: 20%パーセント
予測場所 - Sydney Olympic Park, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
明日 - 月曜日, 2 2月
Cloudy.
分: 18C マックス: 25C
降雨の可能性: 20%パーセント