近期公告
  • 23rd 六月 2025, 23/06/25 Monday DECODE VUE Cronulla. 7am Site ToolBox Meeting L2

    All workers must be inducted on site 7am
    All workers must sign IN and OUT
    All workers must have full P.P.E
    NO PARKING IN WORK ZONE ON KINGSWAY; FOR DELIVERIES ONLY!
    All deliveries & crane lifts to be coordinated with Decode management & scheduled in on delivery board in site office,
    NO on the spot lifts.

    Monday 23/6/25
    Crane: Scaffold Delivery L1 P4 & FormWork Lifts
    As per Crane Board
    Formworker Install L2 & L3 continues,
    L2 & L3 works ongoing Install @ Height as per Code. Catch deck with Perimeter Scaffold.
    Secure loose items w wind. Handrails installed, FormWorker only areas.
    Keep access ways clear.
    Deliveries lifted off Kingsway w Traffic Control. Materials pre slung.
    Scaffolder building L1 P4
    Steelfixer continues
    PT ongoing
    Plumber & Electrician & Sprinklers continue with works.
    B1 Movement of Formwork material, Lifted out through Peno.
    Formworker clean rubbish in Basement bins provided.
    B1 Delineated worker areas, Forklift & Telehandler operating.
    Telehandler on the Ramp.

    High Risk Areas:
    Telehandler Ramp & Forklift lift & shift in Basement B1
    People give way to Forklift w working area delineated & signed.
    Deliveries w Traffic Control
    Crane Lifts & Tower Cranes
    Scaffolder WAH
    Formworker Works at Height; Catch deck required and FormWork leading edges precautions in place,
    L2 & L3 Exposed to Wind gusts, care with formwork sheets & housekeeping
    Strap & nail down sheets at smoko & end of the day
    PT Stressing ongoing
    FormWork L2 & L3 Leading edges beyond hand rails FormWorkers ONLY
    WAH precautions Scaffold edge protection
    Exclusion Zone around Peno

    NOTE: Site Access to Offices & amenities has changed.
    Follow plywood path & G Floor access way marked with green & white tape. Via scaffold stairs to toilets, Portaloos on L2 & L3.
    Stretcher Stair to L3.

    - Daily Tasks:
    * cleaning of suspended decks for pour with compressor, sparrow picking & using magnets to pick up excess tie wire
    -site clean/ house keeping All Trades ensure clear access & egress
    - Crane operations / deliveries
    - deliveries for site in Kingsway work zone
    -ALL VISITORS MUST REPORT TO SITE OFFICE VIA GATE 1 CROYDON STREET ENTRY,
    UNDER NO CIRCUMSTANCES ENTRY TO SITE TO BE GIVEN TO NON INDUCTED WORKERS .
    ANY WORKER DOING SO WILL FACE DISCIPLINARY PROCEDURES.
    - all workers must be mindful of truck movements in work zone
    -exclusion zones & bunted off areas are in place for workers safety do not enter unless your authorised personnel to conduct works in allocated areas
    - driveway & street to be kept clean ,Croydon street will require environmental controls/ sediment controls If subcontractors fail to comply NCR’s will be issued
    -sediment controls to remain in gutters on Croydon Street any worker found tampering or moving controls will be issued an NCR
    -Reminder to Workers there is no right turn from Croyden St into the Kingsway. Follow the traffic signage; left turn only.

  • 23rd 十一月 2023, Pre Start- Thursday 23.11.23

    All the workers must be inducted on site
    All the workers must sign in and out
    All the workers must have full P.P.E

    —Daily Task:
    -slabs removal area B to area C/D and load out of demo material
    -site demo stock piles to be loaded out and removed Area D/C
    - building E demo material to be stockpiled and
    loaded out
    - Demo bin changeovers
    - Instant Labour services 2 labourers sorting and cleaning remaining Cronulla mural brick if any,, place on pallets
    Continue sand bagging fence line for sediment controls
    General tidy up of fences, banner mesh weights ect

  • 22nd 十一月 2023, Pre Start Wednesday 22.11.23

    All the workers must be inducted on site
    All the workers must sign in and out
    All the workers must have full P.P.E

    —Daily Task:
    -slabs removal area B to area C and load out of demo material
    -site demo stock piles to be loaded out and removed Area D/C
    - Demo works to continue on building E and finish demo COB
    -elite civil load out material from demo truck & dog &bin changeovers
    - Footpath to be closed where works are ongoing to building E demo and pedestrians diverted by TC's on Kingsway and Abel Pl
    - Decode labourers continue to fill sand bags place on fence line of job and to continue works on cleaning Cronulla sharks bricks and placed on pallets for this weeks brick auction
    -truck load up of remaining hoarding/ scaffolding material onsite Area C

现场天气预报
当前现场天气

最近更新: 22:21
温度: 21C (应用程序 17C)
风速: 37KMH
最大 风: 43KMH @13:21
自上午9点开始降雨: 6.2mm
最低温度: 20C @21:20
最高温度: 30C @13:55 2026/1/31
阵风: 43KMH
最大风力: 54KMH @13:21


观测信息来自 - Bureau of Meteorology
观测位置 - Sydney Airport、NEW SOUTH WALES
时区 - 澳大利亚东部标准时间
预测 - 星期日、1 二月

Wind easing. Cloudy.
最低: 18C 最大: 21C
可能有雨。: 20%


预测信息来自 - Bureau of Meteorology
预测位置 - Cronulla、NEW SOUTH WALES
时区 - 澳大利亚东部标准时间
明天 - 星期一, 2 二月

Cloudy.
最低: 19C 最大: 23C
可能有雨。: 20%


重要现场文件
刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册

刚到这个现场吗?

您知道这个现场的PPE要求吗?

确保您在现场的第一天有正确的安全设备。

查看现场PPE要求

刚到这个现场吗?

到达现场后尽快开始工作。

在您方便的时候在线完成现场注册,节省您的时间。

开始注册

;