SAM01 - Vue - Cronulla
最近のニュースレター
  • 23rd 6月 2025, 23/06/25 Monday DECODE VUE Cronulla. 7am Site ToolBox Meeting L2

    All workers must be inducted on site 7am
    All workers must sign IN and OUT
    All workers must have full P.P.E
    NO PARKING IN WORK ZONE ON KINGSWAY; FOR DELIVERIES ONLY!
    All deliveries & crane lifts to be coordinated with Decode management & scheduled in on delivery board in site office,
    NO on the spot lifts.

    Monday 23/6/25
    Crane: Scaffold Delivery L1 P4 & FormWork Lifts
    As per Crane Board
    Formworker Install L2 & L3 continues,
    L2 & L3 works ongoing Install @ Height as per Code. Catch deck with Perimeter Scaffold.
    Secure loose items w wind. Handrails installed, FormWorker only areas.
    Keep access ways clear.
    Deliveries lifted off Kingsway w Traffic Control. Materials pre slung.
    Scaffolder building L1 P4
    Steelfixer continues
    PT ongoing
    Plumber & Electrician & Sprinklers continue with works.
    B1 Movement of Formwork material, Lifted out through Peno.
    Formworker clean rubbish in Basement bins provided.
    B1 Delineated worker areas, Forklift & Telehandler operating.
    Telehandler on the Ramp.

    High Risk Areas:
    Telehandler Ramp & Forklift lift & shift in Basement B1
    People give way to Forklift w working area delineated & signed.
    Deliveries w Traffic Control
    Crane Lifts & Tower Cranes
    Scaffolder WAH
    Formworker Works at Height; Catch deck required and FormWork leading edges precautions in place,
    L2 & L3 Exposed to Wind gusts, care with formwork sheets & housekeeping
    Strap & nail down sheets at smoko & end of the day
    PT Stressing ongoing
    FormWork L2 & L3 Leading edges beyond hand rails FormWorkers ONLY
    WAH precautions Scaffold edge protection
    Exclusion Zone around Peno

    NOTE: Site Access to Offices & amenities has changed.
    Follow plywood path & G Floor access way marked with green & white tape. Via scaffold stairs to toilets, Portaloos on L2 & L3.
    Stretcher Stair to L3.

    - Daily Tasks:
    * cleaning of suspended decks for pour with compressor, sparrow picking & using magnets to pick up excess tie wire
    -site clean/ house keeping All Trades ensure clear access & egress
    - Crane operations / deliveries
    - deliveries for site in Kingsway work zone
    -ALL VISITORS MUST REPORT TO SITE OFFICE VIA GATE 1 CROYDON STREET ENTRY,
    UNDER NO CIRCUMSTANCES ENTRY TO SITE TO BE GIVEN TO NON INDUCTED WORKERS .
    ANY WORKER DOING SO WILL FACE DISCIPLINARY PROCEDURES.
    - all workers must be mindful of truck movements in work zone
    -exclusion zones & bunted off areas are in place for workers safety do not enter unless your authorised personnel to conduct works in allocated areas
    - driveway & street to be kept clean ,Croydon street will require environmental controls/ sediment controls If subcontractors fail to comply NCR’s will be issued
    -sediment controls to remain in gutters on Croydon Street any worker found tampering or moving controls will be issued an NCR
    -Reminder to Workers there is no right turn from Croyden St into the Kingsway. Follow the traffic signage; left turn only.

  • 23rd 11月 2023, Pre Start- Thursday 23.11.23

    All the workers must be inducted on site
    All the workers must sign in and out
    All the workers must have full P.P.E

    —Daily Task:
    -slabs removal area B to area C/D and load out of demo material
    -site demo stock piles to be loaded out and removed Area D/C
    - building E demo material to be stockpiled and
    loaded out
    - Demo bin changeovers
    - Instant Labour services 2 labourers sorting and cleaning remaining Cronulla mural brick if any,, place on pallets
    Continue sand bagging fence line for sediment controls
    General tidy up of fences, banner mesh weights ect

  • 22nd 11月 2023, Pre Start Wednesday 22.11.23

    All the workers must be inducted on site
    All the workers must sign in and out
    All the workers must have full P.P.E

    —Daily Task:
    -slabs removal area B to area C and load out of demo material
    -site demo stock piles to be loaded out and removed Area D/C
    - Demo works to continue on building E and finish demo COB
    -elite civil load out material from demo truck & dog &bin changeovers
    - Footpath to be closed where works are ongoing to building E demo and pedestrians diverted by TC's on Kingsway and Abel Pl
    - Decode labourers continue to fill sand bags place on fence line of job and to continue works on cleaning Cronulla sharks bricks and placed on pallets for this weeks brick auction
    -truck load up of remaining hoarding/ scaffolding material onsite Area C

現場天気予報
現在の現場の天気

最終更新日時: 22:21
温度: 21C (アプリ 17C)
風速: 37KMH
最大風速: 43KMH @13:21
午前9時からの雨: 6.2mm
最低気温: 20C @21:20
最高気温: 30C @13:55 2026/01/31
突風: 43KMH
最大突風: 54KMH @13:21


観察元 - Bureau of Meteorology
観察場所 - Sydney Airport, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
予測 - 日曜日, 1 2月

Wind easing. Cloudy.
: 18C マックス: 21C
降雨の可能性: 20%パーセント


予測の出典 - Bureau of Meteorology
予測場所 - Cronulla, NEW SOUTH WALES
タイムゾーン - オーストラリア東部標準時
明日 - 月曜日, 2 2月

Cloudy.
: 19C マックス: 23C
降雨の可能性: 20%パーセント


重要な現場書類
現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に初めてですか?

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

;